11 Free Renovation Budget Worksheets (Printable Set)

Eleven blank worksheets I use before signing a renovation quote. Print them once and reuse them on every project — the tables are deliberately plain so they survive a photocopier and a site visit.

Get them as a PDF by email

Planning ranges are in US dollars and are illustrative. Always price against written local quotes; nothing here is a substitute for a licensed contractor or an engineer.

A.1 Project brief

One page that fixes the scope before anyone prices it. The exclusions line is the one that prevents change-order arguments.

FieldYour answer
Rooms / dimensions
In / out
Finish level + reference
Fixed constraints
Done criteria
Exclusions
Two corners I am holding
Safety / function / appearance items

A.2 Budget shell

Five mandatory lines. Every amount needs the assumption behind it and the quote it came from.

LineAmountAssumptionsQuote ref
1. Materials
2. Labour
3. Allowances
4. Fees / services
5. Contingency
Total

A.3 Contingency score and reserve log

Size the reserve from eight risk factors, then log every draw so the balance is always visible.

Risk 1-8 (tick)Total scoreReserve %Reserve amount

Reserve draw log

DateReasonDrawBalance

A.4 Splurge / save matrix

For each element, write the premium option and the cheaper one before you decide. The decision column is the whole point.

ElementSplurge optionSave optionDecisionAmount

A.5 Finish selection and takeoff

Quantities before quotes. Waste percentage and lot number decide whether two rooms match.

AreaProduct$/sq ftWaste %QtyPrepInstallTotalLot

A.6 Rent or buy

Break-even days = (purchase - resale + extras) / rental per day. If you need it longer than that, buy.

ToolPurchaseResaleExtrasRental/dayBreak-even daysDays neededDecision

A.7 Three-bid comparison

Put the three bids on the same lines, then normalise the scope. The cheapest total is often the one with the largest exclusions.

LineBid ABid BBid CNotes

A.8 Timeline and long-lead items

Duration plus buffer, and what each phase waits for. Cure times and permits belong here, not in your head.

PhaseStartDurationBufferDepends onActual

Long-lead items

ItemOrder byLead timeNeededOrderedDelivery

A.9 Purchase tracker

One row per lot. Return window and storage location are the two columns people add after the first mistake.

Item / SKUSupplierOrder #QtyLotCostDueReceivedReturn byStored

A.10 Change-order log and punch list

A numbered, signed change order is the only thing that stops a verbal instruction becoming a billing argument.

#DateChangeCostDays addedApproved by

Punch list

Punch itemLocationWhoDueRechecked

A.11 Final reconciliation

Planned versus actual, line by line, with the reason. This is the only document that makes the next project cheaper.

LinePlannedActualVarianceWhy